Türkiye-based Rönesans Holding has brought its construction, engineering and long-term infrastructure businesses together under Rönesans Altyapı, a new platform with a construction backlog of €8.7 billion as of June 30, 2026. The platform includes Dutch contractor Ballast Nedam and Heitkamp, which operates in Germany and Switzerland.

Rönesans Altyapı has identified four strategic business areas: social infrastructure, transportation infrastructure, renewable energy and digital infrastructure. Kemal Sağlam has been appointed CEO of the new structure.

€2 Billion Dutch Bridge Project

Türkiye and the Netherlands will serve as the platform’s two main markets. In the Netherlands, Ballast Nedam is involved in transportation infrastructure, water management, modular construction, renewable energy infrastructure and industrial projects.

One of its major projects is the New Merwede Bridge, undertaken by the ALSÉÉN joint venture between Ballast Nedam and Fluor. The project is valued at €2 billion, including €1 billion allocated to the bridge, which is scheduled to open to traffic in 2030.

Data Center Investments Could Reach $3 Billion

Rönesans Altyapı has partnered with Digital Realty to develop data center infrastructure in Türkiye. Construction of its first data center campus has begun in Ankara’s Temelli district, with the initial phase planned to provide more than 22 MW of IT capacity and over 10,000 square meters of white space. The first phase is targeted to become operational in 2028.

The company plans to develop another campus in Istanbul. Once all phases are completed, the platform could reach 204 MW of IT capacity, with total investment potential of up to $3 billion at the joint-venture level.

Renewable Energy Capacity Targeted at 2,000 MW

Rönesans Altyapı also plans to expand its renewable energy portfolio. Its operational installed capacity rose from 166 MW in 2023 to 577 MW in the first half of 2026, following the expansion of its partnership with TotalEnergies.

The company aims to reach approximately 1,400 MW of operational installed capacity by 2028 and around 2,000 MW in the medium term. It also plans to increase the capacity of the Gökçedağ Wind Power Plant from 130 MW to 192.5 MW through a modernization investment.

Healthcare Infrastructure Expansion Abroad

Rönesans has also begun expanding its public-private partnership healthcare model internationally. Six city hospitals developed in Türkiye under the model have a combined capacity of approximately 9,300 beds.

Construction is continuing on a 630-bed hospital in Kokshetau, Kazakhstan, while the company is also exploring opportunities in Uzbekistan and Egypt.

Rönesans Holding Chair İpek Ilıcak Kayaalp said the group had generated $50 billion in revenue from international projects to date. Over the past decade, the company has also delivered more than $2 billion worth of goods and services from Türkiye to its overseas projects, supporting domestic suppliers and subcontractors.

Source: Patronlar Dünyası/ Prepared by: İlayda Gök